Fraser Coast Airport Renewal Project

Latest News

  • Airport Renewal Project Update No.8 – 23/12/20

    Christmas shutdown 18/12/20 – returning 4/1/21

    All works have now finished for 2020. There will be some hydroseed watering during the Christmas and New Year period, with works due to recommence 4 January 2021.

    The final grooving has been delayed due to mechanical issues and at this stage will be recommencing 15 January 2021. Line marking will occur upon completion of the grooving (approximately 30 January 2021).

    As mentioned in our last update, the grooving works will have to occur at night to avoid disruption to flights and minimise impact on residents and visitors using commercial passenger flights. While there will be some noise generated from the grooving, these works will not be as noisy as the laying of the asphalt and major works phase. All other works (i.e minor lighting etc) will be completed during the day.

    Please visit the project page for more detailed information on the project:

    https://frasercoast.engagementhub.com.au/fraser-coast-airport-renewal-project 

    If you have any questions or would like to discuss the project please do not hesitate to contact the Project Team:

    Contact Information:

    E| enquiry@frasercoast.qld.gov.au   (Subject line: Airport Renewal Project)

    P| 1300 79 49 29                                     After Hours P| 1300 79 49 29

     

    The next update will occur in January 2021.

    We acknowledge our local residents and airport stakeholders and thank you for your patience and understanding while this important work has been carried out.

    We wish you a safe and Merry Christmas & a Happy New Year.

    Kind Regards,

    Community Development and Engagement (on behalf of the Airport Project Team)

    Fraser Coast Regional Council

    T| 1300 79 49 29   E| enquiry@frasercoast.qld.gov.au