Maryborough Revitalisation

Latest News

  • Update - Maryborough CBD Revitalisation Project - Stage 2 - Kent Street (Lennox Street to Adelaide Street) and Maryborough Administration Centre Demolition

    Maryborough CBD Revitalisation Project

    Northern Side

    • Street furniture installation.

    Southern Side

    • Test sampling of rendering for capping blocks completed.  Further work will be completed on the rendering of the capping blocks;
    • Light pole footing work completed;
    • Electrical wiring and connection will be completed;
    • Quality of subgrade currently being investigated to ascertain progressing with further excavation of the subgrade prior to kerb and channel construction;
    • Kerb and channel construction including completion of kerb ramps;
    • Commencement of footpath works.

    Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.

     

    Maryborough Administration Centre Demolition

    • The internal demolition and strip out of the Administration building is progressing.

    Should you wish to discuss any aspect of the project please contact:

    Maryborough Administration Centre – Demolition Works

    Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au