  • Works to be Undertaken – 28 January to 7 February, 2020

    Works to be Undertaken – 28 January to 7 February, 2020

    Northern Side

    • Installation of electrical and communication conduits
    • Installation of irrigation network
    • Placement of kerb and channel, roof water and gully units

    Suthern Sideo

    • Construction of Retaining Wall footing, with wall to commence after curing of footing, excluding rendered capping blocks.

    Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during the night time works.