Fraser Coast Airport Renewal Project

Latest News

  • Airport Renewal Project Update - 16/10/20

    Majority of works to be completed in days - not weeks 

    The last of the runway asphalt works is scheduled to finish over this weekend, with plant demobilisation to happen over the next two weeks. The plant demobilisation is scheduled to take place during the day. (weather permitting etc)

    Grooving Works

    The final grooving works are schedule to occur in either early December or mid January - taking approximately two weeks (weather permitting). The asphalt needs to cure for eight weeks before the grooving can take place. Council will update stakeholders closer to the time.

    Please visit the project page for more detailed information on the project:

    https://frasercoast.engagementhub.com.au/fraser-coast-airport-renewal-project

    If you have any questions or would like to discuss the project please do not hesitate to contact the Project Team:

    The next update will occur when there is more information about the start of the grooving works.

    Council would like to take this opportunity to thank you for your continued patience while this important work has been carried out.

     

    Kind Regards,

    Community Development and Engagement (on behalf of the Airport Project Team)

    Fraser Coast Regional Council

    T| 1300 79 49 29   E| enquiry@frasercoast.qld.gov.au