Hervey Bay Library & Admin Centre Inc Disaster Resilience Centre

The Fraser Coast Regional Council, in partnership with the Australian Government, is building a better lifestyle for Hervey Bay and creating a revitalised world-class city centre and civic hub.

The backbone of the city centre revitalisation will be a new regional library building and Council administration centre, located on the corner of Main Street and Torquay Road in Pialba.

It will be a community hub where people can come together to learn, to socialise and to benefit from centralised Council services. It will also include a Disaster Resilience Centre, where Council and government agencies can work together during disasters.

The design concepts have been made available to the community of Hervey Bay for viewing. To view the full report, click on the "Building Concept" button below. You can find more information in a number of fact sheets, and see the latest media release below too.

Construction of a $2.5 million car park extension is underway

Work to revitalise the Hervey Bay City Centre continues to progress thanks to investment from the Albanese Government and Fraser Coast Regional Council, with construction of a $2.5 million car park extension underway.

Hervey Bay’s tallest crane officially named HERCULES

Hervey Bay’s tallest crane has been named HERCULES following a fun and creative naming and colouring competition for local primary school students and kindy kids.

  • Stage 1

    Due diligence - completed

  • Stage 2

    Functional brief - completed

  • Stage 3

    Project brief, development & site urban design - completed

  • Stage 4

    Concept design, community consultation - completed

  • Stage 5

    Schematic design & DA submission - completed

  • Stage 6

    Detailed design (30%) - completed

  • Stage 7

    BA/ tender documentation completed

    EOI: complete

    ECI tender: complete

    ECI tender agreement award: complete

    Building approval: pre-Dec 23

  • Stage 8

    ECI and Design Development (incl D&C GMP finalisation)

    D&C lead contract award: complete (Nov 23)

  • Stage 9

    Design & Construct contract - August 23-June 26 (Gross PC)

  • Stage 10

    Defects liability - 12 months from Gross PC