    Northern Side

    • Placement of kerb and channel;
    • Telstra Pit works;
    • Construction of footpath.

    Southern Side

    • Continuation and finalisation of construction of City Hall block Retaining Wall;
    • Commencement of straightening works of City Hall Stair Columns;
    • Commencement of City Hall Brick Retaining Wall excluding rendered capping blocks.

    Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.

    Council thanks you for your co-operation and understanding during the completion of these works.