The first stage of the major works between Burrum and Howard Streets will commence in March 2024, and continue throughout the year.
The second stage of the redevelopment of the Burrum Heads Caravan Park inside the property boundary between the Burrum River and Burrum Street will continue in 2025.
The construction works will include new roads and services that will be widened and relocated. New buildings include a manager’s building, amenities, BBQ areas and a camp kitchen.
Trees being removed will be replaced on at least a two for one basis as part of the landscaping works. Replacement trees will include native trees to match the rest of the caravan park and foreshore.
Council thanks everyone for their patience during these works.
For more information about the redevelopment of the four Council-owned caravan parks, go to frasercoast.engagemenethub.com.au/caravan parks.com.au.