Remediation of the demolition site for the Maryborough Administration Building and Toy Library has started this week. Minor works to take place – progressing to major works in approximately two weeks. It is anticipated the completion will be late December. Site fencing will remain in place until the remediation works are finished in December.
The works will consist of:
Should you wish to discuss any aspect of the project please contact the Corporate Projects Team:
1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Thank you for your continued patience during this project.
Current Status of Site:
Community Development and Engagement (on behalf of the Project Team)
Fraser Coast Regional Council
T| 1300 79 49 29 E| enquiry@frasercoast.qld.gov.au
Final works are still underway on site of the Maryborough Administration demolition. It was identified further site clearing was needed and new soil will be brought in and contoured on the site.
The project team anticipate site works will now be completed - approximately 17 August.
The site will then be ready for site remediation – more information to come on this.
The School of Arts extra works – as mentioned previously – all depends on the approval from the Queensland Department of Environment and Science.
Should you wish to discuss any aspect of the project please contact the Corporate Projects Team:
1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Thank you for your continued patience during this project.
Kind Regards,
Community Development and Engagement (on behalf of the Project Team)
Fraser Coast Regional Council
T| 1300 79 49 29 E| enquiry@frasercoast.qld.gov.au
The demolition is almost complete with 98% of all above ground structures removed, with works progressing well over the last few weeks.
Site clearing has commenced and removal of foundations will follow, with completion in approximately 3 weeks (approximately 31 July).
The next step will be site remediation, including turf laying etc.
Some further works will have to be conducted in the coming months in relation to the neighbouring School of Arts Building – further information to come.
The timing of these works will depend upon having approval from the Queensland Department of Environment and Science.
Should you wish to discuss any aspect of the project please contact the Corporate Projects Team:
1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Thank you for your continued patience during this project.
Kind regards,
Project Team
All the major works associated with the Kent Street CBD Revitalisaton project are now complete with orders pending on the trees to be planted and the power boxes. Both these items will be installed once they arrive which will complete all the works on this project.
Traffic will return to a two way traffic flow from 9.00 a.m. this morning (27 May 2020) with pedestrian access being permitted from midday today (27 May 2020) following the final clean-up of the footpaths etc.
Council thanks everyone for their patience during completion of this project.
The following works and staging is planned for the next two weeks (weather dependant) for the above projects:-
Maryborough CBD Revitalisation Project
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) for next week. Practical Completion for this project Is programmed for 22 May, 2020 and it is expected that the majority of works will be completed on this project at that time. Should this be the case, traffic flow from 22 May 2020 will return to a two way traffic flow from this date.
The electronic power boxes and the trees for this project have been ordered; however, the supply of these items are still pending and accordingly, the installation of these items will be completed when supply arrives.
Maryborough Administration Centre Demolition
The internal demolition and strip out of the Administration building is progressing.
Should you wish to discuss any aspect of the project please contact:
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Council thanks you for your co-operation and understanding during the completion of these works.
The following works and staging is planned for the next two weeks (weather dependant) for the above projects:-
Maryborough CBD Revitalisation Project
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Maryborough Administration Centre Demolition
The internal demolition and strip out of the Administration building is progressing.
Should you wish to discuss any aspect of the project please contact:
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Council thanks you for your co-operation and understanding during the completion of these works.
The following works and staging is planned for the next two weeks (weather dependant) for the above projects:-
Maryborough CBD Revitalisation Project
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Maryborough Administration Centre Demolition
The internal demolition and strip out of the Administration building is progressing.
Should you wish to discuss any aspect of the project please contact:
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Maryborough CBD Revitalisation Project
Northern Side
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Maryborough Administration Centre Demolition
Should you wish to discuss any aspect of the project please contact:
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Maryborough CBD Revitalisation Project
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Maryborough Administration Centre and Toy Library Demolition
Maryborough Administration Centre
The internal demolition and strip out of the Administration building has now commenced.
Toy Library
The building that housed the Maryborough Toy and Special Needs Library has now been demolished.
Should you wish to discuss any aspect of the project please contact:
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Maryborough CBD Revitalisation Project
Northern Side
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Should you have any queries relating to the Stage 2 Maryborough Revitalisation Kent Street project, please do not hesitate to contact Council's Coordinator Programming and Communication Ph. 41905742 or via email enquiry@frasercoast.qld.gov.au.
Maryborough Administration Centre and Toy Library Demolition
Works has commenced this week on the demolition of the former Council administration building in Maryborough. The works are due to be completed by the end of July, weather permitting.
The tender for the building demolition was awarded to Demex Pty Ltd, a south-east Queensland company that specialises in major demolition projects and asbestos removal.
Demex’s tender submission showed experience in difficult and sensitive demolitions, while they also have an in-house, specialist asbestos removal team.
Examples of previous projects Demex has worked on include the Cairns Performing Arts Centre, the Jupiter’s Hotel and Casino Refurbishment, the Dubbo Base Hospital Redevelopment and the Gold Coast Cultural Precinct.
The demolition process will start with the removal of the first floor interior walkway adjoining the School of Arts Building and the removal of asbestos in both the old administration building and the old toy library.
This will take about four weeks and include 24-hour air and noise monitoring during the works.
The next stage will be the demolition of structures from the back to the front using hydraulic pincer crushers and dust suppression. This will take about 11 weeks.
The last stages will include the construction of a concrete retaining wall, which will take about a week and the site remediation, including turf laying, which is expected to take another week.
Council is committed to maintaining a presence in the Maryborough CBD and will develop a new administration centre and library on the same site.
The development of a new Maryborough administration centre will be a long process, with demolishing the old building just the first step.
Council has started the concept design work and is currently conducting an accommodation review, which will help determine the requirements for new administration centres in both Maryborough and Hervey Bay.
The development of a new Council administration building in the Maryborough CBD will help with the revitalisation of the city centre and act as an economic catalyst for further business investment.
Car Parking
A car parking area behind the old administration building is now barricaded off for the duration of the demolition period, and there is no access to Kent Street or Adelaide Street via the fenced work area.
Council has insisted on a number of measures to minimise the impact of the building demolition work on the community, including no use of large hydraulic jack hammers, air quality monitoring and traffic control.
Should you wish to discuss any aspect of the project please contact:
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
MEDIA RELEASE
27 February 2020
The demolition of the former Fraser Coast Regional Council administration building in Maryborough starts next Monday (2 March) and is due to be completed by the end of May.
CEO Ken Diehm said an independent engineering report found the building at 431 Kent Street had reached the end of its working life and had to be demolished.
“The report concluded that the 50-year-old building was unusable as it had a number of structural defects, required a new air-conditioning system and needed upgrades to the water supply and sanitary drainage, an overhaul of electrical systems and the removal of asbestos,” he said.
“The building that housed the Maryborough Toy and Special Needs Library will also be demolished with the staff and toys relocated to within the Maryborough Library at the start of the year.
“It’s pleasing that the relocation of the toy library has been embraced by the community with toy loans rising from an average of 46 per week to 75 a week since the move.”
Director of Infrastructure Services Davendra Naidu said street revitalisation works in the Maryborough CBD were progressing well with the installation of underground infrastructure on the northern side of Kent Street complete, and footpath concrete pours now commencing.
“Weather permitting, the concrete footpath works on the northern side of this project will be finalised before the start of the demolition of the administration building,” he said.
“Works are also progressing on the southern side of Kent Street with the straightening of the City Hall stair columns and the remaining tie-in of the block retaining wall complete, which allows the brick façade retaining wall to commence.
“These street revitalisation works, which have been part funded by the Queensland Government through the Building our Regions program, are scheduled for completion by early May.”
Mr Diehm said a car parking area behind the old administration building had been barricaded off, and there would be no access to Kent Street or Adelaide Street via the fenced work area.
“Council has insisted on a number of measures to minimise the impact of the building demolition work on the community, including no use of large hydraulic jack hammers, air quality monitoring and traffic control,” he said.
“In addition, the finished site will be grassed to prevent erosion and sediment run-off to protect our waterways.
“We recognise that this work will cause some inconvenience and we thank everyone in advance for their patience as the end result will be a better and brighter Maryborough CBD.”
Mr Diehm said Council was committed to maintaining a presence in the Maryborough CBD and would develop a new administration centre and library on the same site.
“The development of a new Maryborough administration centre will be a long process, with demolishing the old building the first step,” he said.
“Council has started the concept design work and is conducting an accommodation review which will help determine the requirements for new administration centres in both Maryborough and Hervey Bay.
“With both Maryborough and Hervey Bay libraries not having enough space to meet the needs of our growing population and to meet State Government public library grant requirements, we’re also looking to incorporate a new library facility into the Maryborough administration centre.”
Maryborough CBD Revitalisation Project
Northern Side
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Maryborough Administration Centre and Toy Library Demolition
The tender has been awarded for the demolition of the former Council administration building in Maryborough. Works will start on Monday, 2 March and are due to be completed by the end of May.
The building that housed the Maryborough Toy and Special Needs Library will also be demolished. The staff and toys have now been relocated to within the Maryborough Library.
It’s pleasing that the relocation of the toy library has been embraced by the community with toy loans rising from an average of 46 per week to 75 a week since the move.
A car parking area behind the old administration building will be barricaded off from Thursday 27 February, for the demolition period, and there will be no access to Kent Street or Adelaide Street via the fenced work area (see attached Map).
Council has insisted on a number of measures to minimise the impact of the building demolition work on the community, including no use of large hydraulic jack hammers, air quality monitoring and traffic control.
Should you wish to discuss any aspect of the Maryborough Administration Centre and Toy Library Demolition project please contact:-
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Northern Side
Southern Side
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during night time works. There will be a mixture of day/night works for the next two weeks for this project.
Council thanks you for your co-operation and understanding during the completion of these works.
Full details relating to this project and the upcoming Maryborough Administration Centre Demolition can be viewed via the link below:-
https://frasercoast.engagementhub.com.au/maryborough-revitalisation
Works to be Undertaken – 28 January to 7 February, 2020
Northern Side
Suthern Sideo
Traffic arrangements relating to this project will remain unchanged with Kent Street open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during the night time works.
Council has engaged the services of an external qualified Project Arborist to assist Council with procedures to limit, where possible, the effects of the removal and reconstruction of the City Hall retaining wall on the existing fig trees and cocos palms’ current health and condition.
Prior to works on this project commencing, a Tree management Plan of the fig trees and cocos palms was completed. Within the Report, it was been ascertained that root pruning of the trees will be required to accommodate the excavation works for the construction process. The Report noted that the resulting root loss is likely to accelerate the decline that is already evident in the trees’ health. The Report indicated that the existing two fig trees located closest to Lennox Street which front Kent Street are considered to be in a fair/poor condition with both trees already displaying reduced vigour. The Report also noted that a fig tree on the Lennox Street frontage to the site had succumbed to Phellinus noxius, an aggressive root rot decay pathogen that attacks the roots of trees, especially figs. This is a naturally occurring fungal that is easily spread through movement of soil, this can be by foot or tool.
Tree protection measures/procedures will be undertaken as part of the works to remove and reconstruct the City Hall retaining wall, under the guidance of the Project Arborist, with a future care management and replacement program being established for the entire Town Hall Green, including the fig trees and cocos palms located within the City Hall precinct area.
Stage 2 works for the Maryborough CBD Revitalisation Project in Kent Street from Lennox Street to Adelaide Street will commence on Sunday, 12 January 2020 at 6.00 p.m.
The following works and staging is planned for the first two weeks of this 17 week construction project:-
Northern Side
Southern Side
The Traffic Guidance Schemes (TGS’s) for vehicular and pedestrian traffic relating to completion of the project is attached. As indicated in the attached TGS’s, Kent Street will be open to one way traffic flow in an easterly direction (Lennox to Adelaide Sts) during the day with a full road closure from 6.00 p.m. to 6.00 a.m. applying during the night time works.
Council thanks businesses and residents for their co-operation and understanding during the completion of these works.
Residents are encouraged to register through this project page, to keep up to date with the details of the project, prior to the works commencing and during the project.
If this is your first time using Council’s Engagement Hub, please register via this link to create an account: https://frasercoast.engagementhub.com.au/register
When prompted, create a username and password of your choice and provide a valid email address. Please also choose Maryborough Revitalisation Project – so we know you are interested in this project specifically.
If you have already registered and wish to be included in project updates, please update your preferences by following this link: https://frasercoast.engagementhub.com.au/users/update_user_profile
Council is committed to minimising impacts to the community and businesses. All works will be monitored closely by Council and the contractors with regular communication with stakeholders and nearby residents and businesses.
The planned works for these projects will run in parallel and will be coordinated to minimise disruptions to the community.
Residents and Stakeholders are encouraged to register through this project page to keep up to date with the details of the project prior to the works commencing. This page will also remain open during the works as a resource for community members and stakeholders to keep up to date during the project.
To ensure that residents and stakeholders are adequately informed, Council will communciate in a number of ways.
Council will visit businesses and residences in the immediate vacinity of the works in December to discuss the project.
Council will also be writing to residents and stakeholders at key milestones of the project.
Council will update registered stakeholders regularly every two weeks once works commence via an email newsletter. The project page will also send those updates etc to registered members during the project.
Council will write to residents and businesses before Christmas. Council will also write to residents and stakeholders again once the outcome of the demolition works tender process is known with any updated information.
If this is your first time using Council’s Engagement Hub, please click on register (or https://frasercoast.engagementhub.com.au/register) to create an account. When prompted, create a username and password of your choice and provide a valid email address. Please also choose Maryborough Revitalisation Project – so we know you are interested in the project specifically.
If you have already registered and wish to be included in project updates, please update your preferences by following this link: https://frasercoast.engagementhub.com.au/user
Maryborough CBD Revitalisation – Kent Street (Lennox to Adelaide Streets)
Janaury 2020 - May 2020 (approximately 17 weeks): * subject to change dependent on delays out of the control of Council and the contractors.
Maryborough Administration Centre – Demolition Works
March 2020 - May 2020: * subject to change dependent on delays out of the control of Council and the contractors.
Future Works - New Maryborough Administration Building and Library
Mid 2020 Start: The project, inlcuding community & stakeholder engagement, is due to commence in the second half of 2020.
The Stage 2 works, which will commence on the northern side of Kent Street, will be undertaken with a planned completion time of 17 weeks. The Stage 2 works will be undertaken as night works with a full road closure with detour being put in place whilst the works are undertaken. During the day, a one way traffic flow arrangement in an Easterly direction will be implemented. A copy of the layout plan and Fact Sheet relating to the Stage 2 works is located in the Document Library.
The tender for the works closed at the end of November 2019. The tender report is expected to be considered by Council in December.
The works are expected to commence 2 March 2020 and conclude at the end of May 2020. This is subject to change dependent on the tender assessment and delays out of the control of the contractor and Council. A copy of the layout plan and Fact Sheet is located in the Document Library.
Council is committed to minimising impacts to the community and businesses. All works will be monitored closely. An Independent Air Quality Specialist will be engaged during the project to monitor the works. Works will be done during the day and traffic control measures will be in place during working hours for the duration of the works.
The project has been funded through the Queensland Government’s Building our Regions program and by the Fraser Coast Regional Council
Council appreciates the Queensland Government’s funding commitment of $921,960 towards the $2.5 million project to revitalise Kent Street between Lennox and Adelaide Streets, which includes the first stage of work completed earlier this year.
The demolition works of the Administration Building is funded by Council.
The School of Arts building will be closed for the duration of works, and approximately three weeks prior to the works to make the area safe. Approximate closure will occur early next year, sometime in January/February 2020.
The Toy Library will be re-located early January. The new location is not known at this time.
Bus stops closed – Kent St, Maryborough
From Monday 13 January to mid-2020, two bus stops on Kent St near City Hall will be closed as part of Stage 2 of the Maryborough CBD beautification works.
During this time, route 701, 702, 703, 704, 706 and 707 will stop at a temporary stop on Lennox St outside the Bowls Club.
Route 705 will stop at a temporary stop on Kent St, outside the McDowell carpark.
For more information call Wide Bay Transit on 4121 3719.
Should you wish to discuss any aspect of either of these projects, please contact:
Maryborough CBD Beautification – Kent Street (Lennox to Adelaide Streets)
Toni Souvlis: 07 4190 5742 or via email enquiry@frasercoast.qld.gov.au
Maryborough Administration Centre – Demolition Works
Corporate Projects Team: 1300 79 49 29 or via email enquiry@frasercoast.qld.gov.au
Future works will involve the construction of a new Council Administration Centre for Maryborough. No design for the new buildings has commenced as yet. The project, including community engagement, is due to commence in the second half of 2020.
The development of the new site is very important for the community of Maryborough as it will provide modern services and facilities in the heart of the CBD. The site development is part of the Council’s plan to revitalise the Maryborough CBD area.